Home/Products & Services/Rectangular & Circular Pipe Jacking Engineering

Rectangular pipe-jacking machine at the Fuzhou Railway Station transfer passage project.

Engineering Service

Rectangular & Circular Pipe Jacking Engineering

矩形及圆形顶管工程

Large-section rectangular and long-distance circular pipe-jacking construction for rail transit, municipal crossings, utility infrastructure and urban underground-space connections.

面向轨道交通、市政穿越、综合管廊及城市地下空间连接工程提供大断面矩形顶管和长距离圆形顶管施工。

Supplied by Shanghai Tieneng Construction Engineering Co., Ltd.

View Supplier Profile

Overview

Service overview

Tieneng provides low-disturbance pipe-jacking construction where open-cut excavation is constrained by traffic, existing buildings, operating rail transit, utilities, waterways or limited work space. Services cover large-section rectangular pipe jacking and long-distance circular pipe jacking, with equipment and construction parameters selected according to section geometry, drive length, ground conditions, groundwater, settlement limits and launch/reception conditions.

铁能面向交通、既有建筑、运营轨道交通、地下管线、水体或施工场地限制下不宜大面积明挖的工程,提供低扰动顶管施工。业务涵盖大断面矩形顶管和长距离圆形顶管,并根据断面形态、顶进距离、地层、地下水、沉降控制及始发接收条件配置设备与施工参数。

Scope

Service scope

Key components that may be provided for relevant engineering scenarios.

  • Large-section rectangular pipe jacking for underground passages
  • Long-distance circular pipe jacking for water, wastewater and utility crossings
  • Jacking guidance, friction reduction, intermediate jacking and face-pressure control
  • Launch and reception planning under constrained shaft and site conditions
  • Settlement monitoring and protection measures for sensitive crossings
  • 地下通道大断面矩形顶管施工
  • 水务、污水及市政工程长距离圆形顶管施工
  • 顶进导向、减摩、中继顶进及掌子面压力控制
  • 受限工作井及场地条件下的始发、接收组织
  • 敏感穿越条件下的沉降监测与保护措施

Scenarios

Applicable project scenarios

Typical project conditions where this offering may be relevant.

  • Metro station entrances, transfer passages and underground pedestrian connections using rectangular pipe jacking
  • Pedestrian or vehicular passages beneath existing roads and commercial districts
  • Long-distance circular pipe jacking for wastewater and utility infrastructure
  • Utility corridors and underground-space connections requiring minimal surface disruption
  • Sensitive crossings beneath roads, rail transit, waterways and existing utilities
  • 采用矩形顶管建设的地铁出入口、换乘通道及地下人行连接工程
  • 既有道路及商业区下方人行或车行通道
  • 污水及市政管线长距离圆形顶管
  • 需要降低地面扰动的综合管廊及地下空间连接工程
  • 下穿道路、轨道交通、水体及既有管线等敏感穿越工程

Offering Details

Technical Details & Applications

  • Technical planning considers jacking force, intermediate jacking stations, friction reduction, face-pressure balance, alignment control, settlement and receiving conditions.
  • Rectangular sections improve usable underground space for pedestrian, vehicular and commercial passages while reducing extensive surface excavation.
  • Equipment resources include rectangular, circular and composite pipe-jacking machines for different section sizes and ground conditions.

Selected Applications

  • Fuzhou Railway Station Transfer Passage: The 109.5 m rectangular jacking passage has an outer section of 10.8 m x 5.9 m and approximately 4.5 m cover. A 10-cutter earth-pressure-balance rectangular jacking machine was used while crossing composite ground, passing above operating Metro Line 1 and beneath major municipal utilities.
  • Baolong MixC / Baima Road Rectangular Passage, Fuzhou: Two parallel double-level passages were constructed using a modular 9.04 m x 9.26 m multi-cutter earth-pressure-balance rectangular jacking machine. Each drive is about 46.5 m long, with cover of approximately 2.5-6.0 m and a gradient of about -5.9%.
  • Tangxun Lake Wastewater Discharge Project, Wuhan: The lake-crossing section totals approximately 3,773.82 m, arranged as four shafts and three drives. The longest single drive is about 1,600 m, using DN4000 reinforced-concrete pipe with an outside diameter of about 4.8 m through complex mixed strata beneath Tangxun Lake.

技术说明与应用案例

  • 技术策划重点考虑顶力、中继间、减摩、掌子面压力平衡、姿态控制、沉降及接收条件。
  • 矩形断面可提高人行、车行及商业通道的地下空间利用效率,并减少大面积地面开挖。
  • 设备资源包括适应不同断面尺寸和地层条件的矩形、圆形及复合顶管设备。

代表性应用

  • 福州火车站换乘通道: 顶管通道长度 109.5 米,外包断面 10.8 米 x 5.9 米,覆土约 4.5 米,采用 10 刀盘土压平衡矩形顶管机施工,需穿越复合地层、上跨运营地铁 1 号线并下穿重要市政管线。
  • 福州宝龙万象广场下穿白马路矩形通道: 采用模块式 9.04 米 x 9.26 米多刀盘土压平衡矩形顶管机施工两条并行双层通道,单条顶进约 46.5 米,覆土约 2.5-6.0 米,坡度约 -5.9%。
  • 武汉汤逊湖污水处理厂尾水排江工程: 穿湖段总长度约 3,773.82 米,采用四井三顶程布置,单程最长约 1,600 米,使用 DN4000 钢筋混凝土管(外径约 4.8 米)穿越汤逊湖下方复杂复合地层。